ALLEGAN WATER TREATMENT PLANT
The contractor constructing the above ground precast storage tank has completed their underground piping work and poured the base slab for the 65’-0 diameter tank. All of the wall panels have been cast on site and are ready to be set in place. The interior formwork was just completed for supporting the cast-in-place concrete roof. The wall panels will now be set and the roof formwork completed for pouring the roof structure. Interior baffles will also be poured after the roof, and equipment and piping installed after concrete work is completed. The tank is scheduled to be complete in early October.Location: Allegan, Michigan
Scheduled Completion: June, 2011
Architect/Engineer: Prein & Newhof
Scheduled Completion: June, 2011
Architect/Engineer: Prein & Newhof

