CALVARY CHURCH ROOF RESTORATION, GRAND RAPIDS

Our Erhardt crew, along with Buist Sheet Metal, began removing Calvary Church's damaged roof materials on May 17 and completed the work on July 22. The metal roof restoration project included the removal and reconstruction of approximately 8,000-square feet of standing-seam metal roof and underlying plywood substrate that were damaged during high winds. The project was completed on time and under budget, all while coordinating with the church’s busy summer events schedule.