The Calvary Church metal roof restoration project includes the removal and reconstruction of approximately 8,000 square feet of standing-seam metal roof and underlying plywood substrate that were damaged during high winds.

An Erhardt crew, along with Buist Sheet Metal began removing the damaged materials in mid-May. A new cedar breather venting system and new plywood decking will be placed, and new standing-seam metal roof panels are scheduled to be installed in the upcoming weeks. The project is on schedule.

Location: Grand Rapids, Michigan
Scheduled Completion: July 2010
Architect / Engineer: Design Plus