ALLEGAN WATER TREATMENT PLANT
The contractor constructing the above ground precast storage tank has completed their underground piping work and poured the base slab for the 65’-0 diameter tank. All of the wall panels have been cast on site and are ready to be set in place. The interior formwork was just completed for supporting the cast-in-place concrete roof. The wall panels will now be set and the roof formwork completed for pouring the roof structure. Interior baffles will also be poured after the roof, and equipment and piping installed after concrete work is completed. The tank is scheduled to be complete in early October.Location: Allegan, Michigan
Scheduled Completion: June, 2011
Architect/Engineer: Prein & Newhof
Scheduled Completion: June, 2011
Architect/Engineer: Prein & Newhof


The Salvation Army Kroc Community Center is nearing completion! Substantial completion is scheduled for the first week of September and the Kroc Center will open its doors to the public late October, 2010.
Erhardt is pleased to be the contractor for the Vacuum Test Lab located at Bissell’s campus in Walker, Michigan. Construction began in early June. The project includes construction of a 1,700 SF laboratory inside Bissell’s existing warehouse space. At the heart of the project is a very extensive mechanical system that will allow Bissell to closely regulate and monitor temperatures and relative humidity inside the laboratory.
Erhardt Construction is pleased to announce that Keith Vandenbergh, Vice President-Estimating, has been appointed to Ferris State University’s College of Business Advisory Board.