PROJECT UPDATE: CONSOLATA MISSIONARY SISTERS RENOVATION
Erhardt Construction is the design/build contractor for the interior renovation of the headquarters of the Consolata Missionary Sisters in Belmont, Michigan. The renovation includes installing an elevator, upgrading the HVAC system, upgrading doors, hardware and finishes, providing fire protection throughout the building, constructing private bathrooms in each residence, and providing an emergency generator. Demolition work started February 1st, 2010.
Location: Belmont, Michigan
Size: 13,734 SF
Scheduled Completion: July 1, 2010