PROJECT UPDATE - Saint Robert of Newminster Parish

The youth center is a large multi-purpose room with a stage and basketball court. It also includes a café, classrooms, and a private prayer room for the congregation’s youth.
Current work on site includes installation of concrete walls and footings. Masonry walls and reinforcing are scheduled to begin the week of December 1st. One of the major building milestones is to have joist and deck completed on the addition by no later than January 1st.
The project will be eight months in duration, wrapping up by June 1, 2009.