PROJECT UPDATE - Lake Michigan Water Filtration Plant

Erhardt began work at the City of Grand Rapids Lake Michigan Water Filtration Plant in West Olive a few weeks ago. This $2.6 million, hard-bid improvement project consists of replacing the underdrains and filter media in filter cells 9-14, along with replacement of the actuators and valves.

Erhardt Construction is self-performing selective demolition, concrete work, and installation of the new underdrains. The project is running on schedule, and completion is scheduled for April, 2009.